How Long Does a Solar Panel Installation Take?

If you’ve decided to join the one million Americans who have chosen to go solar, then you definitely have a lot of good things to look forward to. However, one of the biggest questions is: how long does a solar panel installation take? This blog will go over the steps and the estimated time length of the entire process.

Solar Panel Installation Site Assessment (1 – 2 Weeks)

The initial crucial step of the solar panel installation process is the initial visit to your home for your site assessment. This usually happens within a week or two of signing the contract. Your solar installer will send a team to evaluate the energy needs of your home, as well as take a look at the condition of your electrical panels or anything that may cause any concerns. If your solar system will be going on the roof, then a roof inspection is also conducted. This process usually takes from one to two weeks long.

Getting the Permits (2 – 8 Weeks)

Before any construction gets into place, you will first need to get permission from your city. The good thing is that you don’t have to do anything. Your installer will fill out the forms, so all you have to do is be patient and wait. Depending on many factors, such as where you live, this process can take a couple of weeks or sometimes even stretch out to over a month. Once the project is deemed safe and determined that it adheres to local building codes, you will be ready to go to the next step.

Solar Panel Installation (2 – 3 Days)

The much-awaited step of the journey will happen rather quickly compared to the rest of the steps. The installation of the solar panels will take place for about two to three days. In this step, your solar installers will:

  1. Set up the electrical wiring
  2. Install a racking system
  3. Mount the solar panels

The Final Inspection (1 – 2 Weeks)

Your new solar system has to be reviewed by a local government inspector, and possibly your electric company, before it can be connected to the grid. This is to ensure that your system complies with applicable codes and follows the specifications of your permit. This step can take between one week to one month depending on the efficiency of your local government officials. After the inspection is complete, the inverters will be connected to the grid and your solar system will be ready to go!

How Long Does a Solar Panel Installation Take?

Even though the process of installing solar panels can be lengthy, it will be worth it as you will be saving money on your energy bill with the added bonus of reducing your carbon footprint! To get your solar panels installed, give us a call at (858) 360-8295 or visit our website for a free consultation!